How long does a custom machine tool casting take? At ZZ Casting, a new part takes 3–7 days for pattern making and 20 days for casting and finishing — typically 18–27 days from order confirmation to shipment. Repeat orders are faster because the pattern is retained.
What affects the lead time of a machine tool casting?
Four things dominate: pattern complexity, whether simulation and process design are needed, heat treatment requirements, and inspection depth. A simple worktable can move faster than a ribbed VMC base with internal cavities and strict metallography requirements.
Lead time breakdown
| Stage | Duration | Notes |
|---|---|---|
| Drawing review & process design | 1–2 days | Draft, wall thickness, gating layout |
| Pattern making | 3–7 days | CNC foam pattern on 6 m × 3 m engraver |
| Coating & drying | Included in casting cycle | Automatic wet/dry controlled drying |
| Boxing, sand filling & pouring | 20 days total cycle | 4 boxing stations, 15 sets/day |
| Shakeout, cleaning, heat treatment | Included in casting cycle | Shot blasting + controlled annealing |
| Inspection & shipment | Included in casting cycle | Spectrometer + metallography records |
How can you shorten the schedule?
- Send a complete drawing with material grade and heat treatment specified.
- Confirm quantity upfront — pattern batch size affects scheduling.
- Allow alternate gating locations if the part is symmetry-friendly.
- Keep the pattern with us for repeat orders.
“`mermaid
gantt
title New part vs repeat order
dateFormat YYYY-MM-DD
section New part
Review & design :a1, 2026-01-01, 2d
Pattern making :a2, after a1, 5d
Casting cycle :a3, after a2, 18d
section Repeat order
Casting cycle :b1, 2026-01-01, 18d
“`
Frequently asked questions
For simple parts with an existing similar pattern, sample development can be quicker. Send your drawing and we will confirm the earliest realistic date rather than promise an unachievable one.
Worktables and saddles: 30 pcs/day. Bases and columns: 10 pcs/day. Other components: 40 pcs/day. We can complete up to 15 machine sets of boxing per day and melt up to 35 tonnes daily.
Yes. Patterns are retained so repeat orders skip the 3–7 day pattern-making stage. Batch records and test samples are also archived for two years.